Project Description
 
SE Systems manage the retrofitting of multiple void local authority homes in partnership with Cork City and Cork County Council.
 
SE Systems were appointed as Main Contractor and PSCS to co-ordinate, survey and install the following energy upgrade measures.
 
General Building, Extensions & Renovations | Roofing, fascia & soffit replacement | Plumbing and Heating Installation | Electrical re-wiring | Window & Door Replacements | Cavity Wall Insulation | Attic Insulation | Internal Drylining & Plastering  | Joinery & Carpentry Installation | Painting and Decorating | Mobility and Access Solutions
 
 As Main Contractor and PSCS  for this project SE Systems carried out the following roles.
 
  1. Safe and efficient  delivery of project in compliance with Health & Safety Authority legislation. Daily safety audits were conducted during works by SE Systems designated Safety Officer.
  2. A detailed Site Safety Management Plan, Task Specific Risk Assessments and Detailed Method Statements were prepared and approved by concerned parties prior to commencement of works throughout the  various program stages.
  3. The site was registered and updated with the HSA through the AF1 and AF2 online process.
  4. Daily safety audits were conducted during works by SE Systems designated Safety Officer.
  5. SE Systems as main contractor appointed sub contractors for various trades from their approved contractors list.  Each contractor was fully briefed in their role and were issued with a detailed programme of works outlining start and completion dates.
  6. SE Systems conducted weekly site meetings with all contractors and reviewed works programme until completion.