Project Summary
 
This project was carried out and part funded under SEAI’s Areas Based Scheme 2014.
 
SE Systems installed moderate energy upgrades to 179 local authority homes in various locations in Limerick city.  
 
The scope of the work for this project is as follows.
 
High Efficiency Condensing Gas Boilers  | Fully Integrated Heating Control | Cavity Wall Insulation   | Attic Insulation  | Chimney Draught Stop

| CFL Lighting | Building Energy Ratings

As Main Contractor for this Project, SE Systems carried out the following roles:
 
  1. Project Supervisor Construction Stage.
  2.  Project Management.
  3.  Health and Safety Co-ordinator.
  4.  Appointment and Management of Sub-Contractors to include all trades.
  5.  Scheduling of Work Programmes and administration of weekly site meetings.
  6. Liaise with Tenants and Island Energy Committee on work schedules.
  7. Quality Control of all Energy Upgrade Measures.
  8. Maintenance of SEAI – Technical and Quality Standards.
  9. Issue of External Wall insulation Warranties and Homeowner Aftercare manuals to Homeowners who received External Wall Insulation.
The success of this project lies mainly in the innovative partnership approach taken with all project partners; SE Systems, Limerick County Council, NCE Insulation, SEAI and Emprova.